04 | sub-article-box | Case Report

Service Excellence Kommentare deaktiviert für 04 | sub-article-box | Case Report

Case Report

During the project implementation of our two-phased project in Moldova (Republican Clinical Hospital) we were able to manage the whole process starting with our consulting and engineering services – the procurement process – delivery of equipment from 26 different manufacturers in 13 partial deliveries – supervision of pre-installation & installation works at site and finally training and capacity building.

The efficient realization of our holistic project was achieved by our open project management approach where we tried to share all available information with Hospital leaders, local authorities, construction companies and manufacturers.

Pin It

» Service Excellence » 04 | sub-article-box | Case...
On 24. Oktober 2014
By

« »